Simplifying project sequencing for faster and safer EV battery plant construction

Applying intumescent fire-resistant coatings (IFRM) in controlled shop environments rather than on-site dramatically streamlines project scheduling. Shop application completes 80% of structural steel protection before installation, accelerating the project by 45 days.